How to create a Local I/O Procedure Steps In System Administration, complete the following steps: 1) Select Local I/O from the Access Control menu. 2) Select the Local I/O Function Lists tab, and then click [Add ].
2) In the Name ...
-
Last Updated: 05/06/2025
in OnGuard Ecosystem Security
Symptom: When trying to access License Administration or an access panel’s web configuration page, you might have issues with browsers other than Internet Explorer (IE). Enable IE Mode in the Microsoft Edge browser to allow access to these reso...
-
Last Updated: 03/17/2025
in NetBox Ecosystem
Overview
How to receive NetBox Hourly Support for Expired SUSP
Procedure Steps
Email the required info below to supportorders@honeywell.com for them to send you an invoice for hourly NetBox support.
Required ...
-
Symptom
The following error message appears in the error logs when Database Setup is run: "There was a problem communicating with the license server... Host: localhost Port: 8189 License: (61409504-D2B8-42B1-8E31-4C4E7414CA80) Feature: (...
-
Product Name Non-Production Licensing for OnGuard Access and Video General Information Non-production license : A software license is issued for purposes other than the system owners productions OnGuard integrated, access...
-
Series 3 Reader Interface Modules show readers offline with LNL- 8000 Multiplexers Symptom User may be trying to upgrade series 1 or 2 panels to work with LNL-8000 Star Multiplexer boards downstream. Panels will show offline and not connect or s...
-
Last Updated: 06/05/2025
in OnGuard Ecosystem Database SQL
How to check SQL Server authentication settings Procedure Steps 1) Start Microsoft SQL Server Management Studio. 2) Right-click the server name and select "Properties." 3) Select the Security page. 4) Verify that Server authentication is...
-
This article includes entries in the ACS.ini file in order to handle growing memory utilization of the LS Communication Server service
-
How to set the jumper for reader power on the LNL-2220 and Series 2 LNL-1320 Procedure Steps When setting Jumper J7 on the LNL-2220 or J2 on the LNL-1320 board, always use "PT" for any system with 12 VDC power supplies. Only use the "12V" se...
-
Procedure Steps Under normal circumstances, a Certificate Authority (CA) would generate the server certificates and client certificates. Follow these steps to create a CA, server, and client certificates using OpenSSL: Install and configure Op...